One contract.
Total accountability.
In complex construction, split responsibilities create the conditions for failure. Design & Build consolidates design and delivery under a single point of accountability — removing the gap where problems hide.
Design & Build is not just a contract form. It's a way of thinking.
When Conroy operates as Design & Build contractor, we're not just managing consultants — we're leading the design process from first principles, shaped by buildability, programme logic, and the operational requirements of the end user.
In sectors where the building is also a process environment — a GMP cleanroom suite, a temperature-controlled fulfilment centre, a GIS substation building, a data hall — the design cannot be separated from the delivery. They have to be developed together, by a team that understands both.
Where we engage
across the design stages
We work to RIAI (Republic of Ireland) and RIBA (UK) stage frameworks. On D&B appointments our involvement begins at Stage 1/2 — well ahead of the point where most contractors first appear.
Technical environments we design and build
Each of these building types demands a design process shaped by its operational requirements — not the other way around. The envelope, structure, and services are developed as an integrated system from the outset.
We run the design team. We don't follow it.
D&B only works if the contractor is leading the design process, not reacting to it. Conroy takes the design manager role seriously — it is a distinct, senior function on every D&B project we deliver.
Our design manager chairs design team meetings, owns the design information release schedule, manages RFI and design query responses, and maintains the co-ordination register. At no point does the design process drift ahead of or behind the construction programme without Conroy knowing about it.
How D&B manages risk — and where value is created
Design & Build transfers design risk to the contractor in exchange for certainty of cost and programme. That transfer only works if the contractor actually understands the design risk — and has the capability to manage it.
- Design development risk sits with Conroy post-contract
- Employer's Requirements must be complete and unambiguous
- Provisional sums are minimised through resolved design
- Ground risk allocation is agreed clearly at tender — not assumed
- Change is managed under a defined change control protocol
- Structural system selection — portal vs beam & column vs structural steel
- Envelope strategy — wall and roof system specification
- Services zoning and distribution strategy
- Construction programme sequencing and phasing
- Specification rationalisation without performance reduction
- Design to minimum RIAI Stage 3 / RIBA Stage 3 before CP submission
- Fully priced bill of quantities or elemental breakdown
- Programme to Level 2 minimum
- Schedule of assumptions and exclusions — clearly stated
- Derogation register — agreed before contract execution
- Design for GEP (Good Engineering Practice) from Stage 1
- URS / FDS / DDS aligned with design development stages
- IQ / OQ / PQ commissioning protocols built into programme
- Validation documentation (C&Q) managed within Conroy's QMS
- HPRA / MHRA readiness built into handover deliverables
Ready to discuss a Design & Build project?
Whether you have Employer's Requirements drafted, a site identified, or just a brief — we're experienced in engaging at the right stage and structuring the D&B appointment to suit the project.